Project Management (MG230)
Week-13 Network Problem
Please answers the following questions:
Please use the table below to answer questions A—D.
List all the tasks that are on the critical path.
Find the total time to complete the project (In days)
What is the slack or float of task “D”?
If you increased Task D’s duration from 4 days to 5 days, what
effect will this have on the project?
|
Task |
Preceding Task |
Duration |
|
Start |
N/A |
0 days |
|
F |
Start |
6 days |
|
A |
Start |
10 days |
|
B |
F |
10 days |
|
E |
B,A |
5 days |
|
D |
B |
4 days |
|
End |
D,E |
0 days |